Commercial Interiors
MRc5.1 & MRc5.2
1-2 points |
Regional Materials
Intent: Increase demand for building
materials and products that are extracted and manufactured within the
region, thereby supporting the regional economy and reducing the
environmental impacts resulting from transportation. |
|
Toolbox |
Requirements:
MRc5.1 (20%
Manufactured Regionally) - 1 point
- Use s minimum of 20% of the combined
value of construction and Division 12 (Furniture) materials and
products that are manufactured regionally within a radius of 500
miles.
- Manufacturing refers to the final
assembly of components into the building product that is furnished
and installed by the tradesmen.
MRc5.2 (10% Extracted
and Manufactured Regionally) - +1 point
- In addition to the requirements
of MRc5.1, use a minimum of 10% of the combined value of
construction and Division 12 (Furniture) materials and products
extracted, harvested, recovered, or manufactured within 500
miles of the project.
|